EBZ200 Roadheader for coal mining in Poland

EBZ200 Roadheader for coal mining in Poland

Projects Information

Two of our engineers went to Poland and assisted in installation and commissioning and had technical discussions and trained the company engineers how to operate the roadheader. Our company director also accompanied them

Project Process

  • Equipment model´╝ÜEBZ200
  • Place: Poland
  • Project start time: 2013, 9
  • Project completion date: 2014, 9
  • Customer: Poland customer purchased our roadheader
  • Project type: Tunneling
  • Workface: coal mining
  • Work face hardness: F5
  • Dimensions of tunnel / roadway: 4m wide x 3m height
  • Footage achieved: 10m per day; 120cbm